46 Portman Square

Client: BentallGreenOak

 

Contract Administrator: Knight Frank

Period: November 2023 to January 2024

  • Remove and dispose of off site all blockwork and glazed partition walls providing meeting rooms, offices and tea points in order to leave the premises in an open plan layout.

  • Carefully remove dot and dab plasterboard from all perimeter brick and blockwork walls.

  • Strip up and dispose of off site all carpet and vinyl floor tiles.

  • De-gas, decommission and remove air conditioning system.

  • Repair and redecorate all base build blockwork walls.

  • Install temporary marketing lighting to ground floor and basement.

  • Supply & install new vinyl flooring to all WCs.

  • External redecorations to timber sash windows and front door.

  • Stone repairs and DOFF cleaning to ground floor facade.

8th Floor Aldwych House

Client: Aldwych Investments Limited

 

Contract Administrator: Knight Frank

Period: April 2023 to July 2023

  • Strip out and refurbishment works to 8th Floor of Aldwych House 

  • Stripping out partitions, floor coverings, tea points, tenant installed IT and small power

  • De-tacking and cleaning of raised access flooring 

  • Replacement of damaged ceiling tiles and raised access floor tiles 

  • Reconfiguration of M&E to suit open plan layout

  • Replacement of all spotlights throughout 

  • Full redecoration of walls, ceilings and columns including skirting

Unit 19 Windsor Park Industrial Estate
Wimbledon

Client: Capital Industrial

Period: April 2023 to May 2023

-    Strip out, dismantle and remove from site the dividing wall in the warehouse

- Strip up and remove all carpet and vinyl floor finishes from office area, stairwell, entrance lobby and WCs
-    Strip out all tenant installed small power, data and tenant installed lighting
-    Re-coat the warehouse floor slab with new epoxy paint 

- Install carpet tiles in office area, stairwell and entrance lobby. 
-    Replace vinyl flooring to the WCs
-    General redecorations to walls & lining panels

- Replace all ceiling tiles (grid to remain) in office area
- Install new LED lighting in the warehouse and office areas

- Install new Mitsubishi AC system to upstairs office
-    Test & certify electrical system & emergency lighting

1st Floor The Porter Building
Slough

Client: Spelthorne Borough Council

 

Contract Administrator: Knight Frank

Period: February 2023 to May 2023

  • Remove and dispose of off site all stud and glazed partition walls, doors and frames, providing meeting rooms, offices, break out areas, cupboards, etc. in order to leave the premises in open plan configuration.

 

  • Strip up and dispose of off site all carpet floor tiles and other floor finishes.

 

  • Re-configure heating, cooling and ventilation to suit original CAT A layout and to form a CAT A finish.

 

  • Re-configure the fire alarm system to suit CAT A finish and base build specification.

 

  • Re-configure the general and emergency lighting to CAT A finish and base build specification.

 

  • Remove all glue residue and soiling from raised access floor tiles following removal of the floor finishes.

 

  • Prepare surfaces and apply two coats emulsion paint to base build walls.

9th & 10th Floors Maritime House
Barking

Client: Be First

 

Contract Administrator: Knight Frank

Period: March 2023 to April 2023

  • Strip up all carpet tile coverings, including all adhesives and cart away from site.  

  • Prepare raised floor ready to receive new floor coverings.

  • Supply and install new floor coverings throughout the 9th & 10th floor office space with carpet tiles.

  • Full redecoration of 9th & 10th floors offices.

Unit 6 Merton Road Industrial Estate
Wandsworth

Client: Capital Industrial

Period: January 2023 to February 2023

-    Strip out & dismantle entire mezzanine structure and ground floor meeting room / lobby area
-    Strip out all tenant installed small power, lighting & air conditioning
-    Re-coat the warehouse floor slab with new epoxy paint 
-    Replace the vinyl flooring to the WCs & kitchen
-    General redecorations to walls & lining panels
-    Service & overhaul roller shutter
-    Strip out all tenant installed small power, lighting & air conditioning
-    Test & certify emergency lighting & fire alarm system

Unit 8 Menin Works Industrial Estate
Mitcham

Client: Capital Industrial

Period: January 2023 to February 2023

- Remove stud and blockwork walls 
-    Clean kitchen units and replace cabinet doors
-    Refurbish WCs including new sanitaryware 
-    Re-coat the warehouse floor slab with epoxy paint  
-    Internal decorations including walls and columns
-    Repairs to security bars and doors
-    Service 2no roller shutter doors
-    Reconfigure electrics and lighting to work as one unit
-    Replace glazing of 2no windows at rear

Unit 19 Newington Industrial Estate
Elephant & Castle

Client: Capital Industrial

Period: December 2022 to January 2023

- Strip out all racking, ducting, furniture & chattels

- Strip out tenant installed electrics including data, power & CCTV

- Cladding repairs to flank wall where ducting was removed

- Service roller shutters and install new shutter at rear

- Light decorations of internal warehouse, WCs & kitchen

- Repaint warehouse floor 

Unit 44 Wates Way
Mitcham

Client: Capital Industrial

Period: November 2022 to December 2022

Within the lease renewal the client agreed to replace defective aliminium windows with new uPVC double glazed windows. The works included additional BWIC allowances for protecting the tenant's equipment and undertaking the project while they were in situ.

6th Floor Aldwych House

Client: Aldwych Investments Limited

Contract Administrator: Knight Frank

Period: July 2022 to September 2022

  • Strip out and refurbishment works to two offices in Aldwych House 

  • Stripping out partitions, floor coverings, tea points, tenant installed IT and small power

  • De-tacking and cleaning of raised access flooring 

  • Replacement of damaged ceiling tiles and raised access floor tiles 

  • Replacement of all spotlights throughout 

  • Full redecoration of walls, ceilings and columns including skirting

39 DRURY LANE, COVENT GARDEN

Client: Mercers' Company

Contract Administrator: Knight Frank

Period: May 2022 to July 2022

- Strip out of all tenant belongings incl. all floor coverings

- Repairs / replacement works to the rear elevation walls and windows to basement and ground floor

- Refurbishment of the basement WC including reinstatement of the roof

- Damp remedial works and repairs to the basement floor, incl. levelling screed and repairs to man-hole covers

- Internal repairs and redecorations throughout including shopfront

 - White box fit-out; including new floor coverings, lighting and decorations throughout

16 CRANE STREET, GREENWICH

Client: Greenwich Hospital

Contract Administrator: Knight Frank

Period: January 2022 to March 2022

The proposed works at 16 Crane Street comprised the following internal redecorations and ancillary works including:
- Bathroom replacement
- Kitchen replacement
- Plaster repairs
- Joinery repairs
- Flooring replacement 
- General redecoration 

UNIT B2 TRADE CITY, SYDENHAM

Client: John Lyon's Charity

Contract Administrator: Knight Frank

Period: January 2022 to Februrary 2022

The scope of works included:

• Removal of all tenant fit out including partitions, offices, meeting rooms, tea point and WCs
• Strip out tenants M&E including all lighting
• Overhaul of the roller shutter and sectional doors
• Internal repairs and redecorations including flooring repairs
• External repairs and decorations

5 LANGLEY STREET

Client: Mercers' Company

Contract Administrator: Knight Frank

Period: November 2021 to December 2021

The project at Langley Street comprised the following:

- Undertaking works via abseil

- Roof & parapet repairs

- Adapting rainwater goods (External)

- Installing rainwater goods internally to re-route rainwater to rear elevation drainage

- Masonry repairs

- Ad hoc internal finishes repairs

ONE CANADA SQUARE
LEVEL 30

Client: Canary Wharf Group

Period: April 2021 to July 2021

Level 30 of One Canada Square is the executive floor for Canary Wharf Group (CWG). Following the success of Level 31, Travill Construction was approached to refurbish half a floor (7,000 square foot) including demolition, raised access flooring, partitioning, new SAS Alugrid suspended ceilings, tape and jointing and decorating. The project was carried out in a live office environment and had to be split into three phases to ensure CWG employees could continue to operate at their headquarters. The scope of works included building four large meeting rooms, eight quiet rooms, a breakout area, “chill out” space and 74 desk spaces. The revised layout and additional desk capacity will ensure CWG staff have the necessary space to social distance upon their return to work. During the course of the project we had to adapt to challenging access requirements and changing work hours. We also had to pull off site for over two weeks due to COVID-19 notifications in line with government guidance. In spite of these setbacks we worked day and night to deliver the project within the programme and on budget.

CHELSEA & WESTMINSTER HOSPITAL
CHELSEA WING

Client: Chelsea and Westminster Hospital NHS Foundation Trust 


Phase 1 Period: June 2020 to July 2020

        Phase 2 Period: February 2021 to April 2021

The Chelsea Wing is the private wing of the Chelsea & Westminster Hospital. Due to budgeting constraints Phase 1 focused on refurbishing the main reception, nurses station, two ensuite bedrooms, four clinical rooms and the private patients' passenger lift. The project had to be fully delivered within two weeks in a live hospital environment which presented numerous logistical challenges. Despite this, Travill Construction was able to complete the project on time and within budget without compromising the operation of the wing. Phase 2 of the refurbishment was significantly larger than Phase 1 and got under way in February 2021. After the precise and efficient delivery of Phase 1, Travill Construction was appointed to renovate a further eight ensuite bedrooms as well as some offices and the remaining corridor areas.

ONE CANADA SQUARE
LEVEL 31

Client: Canary Wharf Group

Period: September 2020 to January 2021

Travill Construction was tasked with a 15,000 square foot refurbishment contract on the 31st floor of One Canada Square. This floor had been used as a marketing suite for one of Canary Wharf's residential towers but had since become redundant. The Group wanted to transform the space back into an office floor to be tenanted by their contracting business; Canary Wharf Contractors. The project included the fit out of meeting rooms, print rooms, quiet rooms, open plan desk areas, kitchens, shower units and bathrooms. The construction phase plan was originally 20 weeks but we were delighted to complete a month ahead of schedule as a result of efficient delivery and slick supply chain management. The architect and client were so happy with the quality of work and attitude of Travill Construction's operatives that they have already requested we quote for two further refurb projects. We look forward to building a long lasting relationship with Canary Wharf Group.

BRIXTON HOUSE RECORDING STUDIOS

Client: Ten87 Studios

Period: TBC

Ten87 Studios provide creative workspace and associated facilities for recording artists and music labels. They operate over 40 long term let recording studios in North London. The business is now looking to expand to South London securing space in the basement of the Brixton House development which will house the new Ovalhouse Theatre on the ground floor and Lambeth Council offices on the upper floors. The architectural plans are currently being finalised with a view to build and fit out 30 individual recording studios. Travill Construction look forward to working alongside Ten87 Studios to help them grow their business South of the river.

bottom of page